March 7, 2007
Government Resolution #11
Aleh Negev Rehabilitative Village – Stage II
IT HAS BEEN RESOLVED THAT:
- In continuation of Government Resolution #2032 recognized on June 16, 2002, and following the completion of Stage I of the establishment of the Aleh Negev Rehabilitative Village, the State of Israel will help establish Stage II of the project.
The stated goal of Stage II is the establishment of rehabilitative and paramedical equipment and apparatuses that will offer services to the entire southern population.
- The project will be executed through the Southern Development Authority, with the participation of an inter-ministerial staff including representatives of the following ministries: Vice-Prime Ministry, Welfare, Health, Interior, Construction and Housing, Agriculture, Village Development, Industry, Trade and Labor and National Infrastructures. The staff will oversee and coordinate the planning and execution of activities, the setting of priorities, comprehensive budgetary conditions and timetables, including follow-up and control. Director of the staff will be the head of the Southern Development Authority.
- Government funding is conditional upon the participation of at least 51% of the costs of Stage II by the operating committee.
- Government ministries will participate in Stage II of the project in the following division:
Vice-Prime Ministry:
NIS 1 million to be allocated each year during the years 2007-2008 toward the development of the village
Construction and Housing Ministry:
NIS 1 million to be allocated each year during the years 2007-2008 toward the development of the village
Ministry of the Interior:
NIS 1 million to be allocated each year during the years 2007-2008
Ministry of Industry, Trade and Labor:
NIS 1 million to be allocated each year during the years 2007-2008 to finance transportation expenses of workers
Ministry of Health:
NIS 1 million to be allocated each year during the years 2007-2008 toward the development of paramedical services in the village
Ministry of National Infrastructures:
Through the drainage authority: a grant of NIS 500,000 will be allocated during the year 2007 to connect the drainage system to the village
Aleh Negev Status Report
updated as of June 2007
Background:
The Aleh Negev Rehabilitative Village is being established in the area of the regional council of Merhavim, near Ofakim, on an area measuring 25 acres. Aleh Negev will provide a solution for the needs of the adult population of the network of Aleh centers, as well as for children in the south of Israel in need of a special education framework outside of the home.
The State of Israel resolved in June 2002 (resolution #2032) to help establish Aleh Negev as part of its endeavor to develop the city of Ofakim and the surrounding region.
The project is being executed by the Southern Development Authority and supervised by the relevant governmental ministries.
Stage 1 of the project, estimated at a cost of US$ 23,800,000 (US$1 = 4.2 NIS), has been completed. Fundraising for the rest of the project, estimated at a cost of US$20,000,000, is underway.
Residency continues gradually to ensure successful acclimation. At present, 65 young adults are residents of Aleh Negev.
Concurrently, construction continues on the rest of the buildings and landscaping development.
Construction and Timetable:
I. The Harry and Jeanette Weinberg Residential Units (Om Bros.)
- Three Residential Buildings and Case-Manager Building - construction completed, residents living in the apartments
- Fourth Residential Building - construction in final stages, building to be opened shortly
- Second Case-Manager Building - construction in final stages, building to be opened shortly
II. Vocational Training Center (Om Bros.)
- Wing A - completed and populated
- Vocational workshops include Ceramic and Paper Recycling Workshops. Physiotherapy treatments given on-site during work hours.
- Wing B - to include another three workshops
- Currently up for tender. Construction to begin within two months.
III. Hospital Project (Moshe Avisror and sons)
- Wings A + C - completed, building will be populated by November 2007
- Wing B - construction in final stages, to be completed within two months
IV. Safra Paramedical Center (Moshe Avisror and sons)
- Completed and functioning
- Currently offers paramedical treatments to all residents of Aleh Negev as well as outpatient treatments for special-needs people throughout the southern region
- During the month of May, 120 outpatient treatments were given.
- Staff presently includes physiotherapists, occupational therapists, speech therapists and rehabilitative assistants.
- Services to expand this summer to incorporate the Snoezlen multi-sensory room and the emotional therapy program, including music and art therapy and a social worker and psychologist. The center will also begin treating outpatients requiring rehabilitation.
V. Logistics Center (Moshe Avisror and sons)
- Completed and functioning
- Laundromat processes 250-300 kg of laundry daily
- On-site Kitchen and the Therapeutic Equipment Workshop, where rehabilitative devices and equipment will be created and adapted, to open in four months.
VI. Special Education School Complex
- (Bonei Binyan, through Local Governmental Economic Services Ltd)
- Construction completed
- Building will open at the beginning of the school year Sept. 2007
VII. Peripheral Fence (Pika Infrastructures + Alobra)
VIII. Landscaping and Development of Residential Area (Pika Infrastructures)
- Project completed (includes digging work, walls, gardening, irrigation, fencing)
IX. Landscaping and Development of Rest of Village (Alobra Ltd.)
- Work underway concurrent to completion of buildings
- (Includes development of outdoor areas around the high-dependency wing, paramedical center vocational training center and technical center; continuing paving of roads, sidewalks and lighting installations)
- Anticipated completion: December 2007
X. Rehabilitative Pool
- Project sent out to tender
- Building to begin within three months
- Anticipated completion of project: January 2009
- XI. Therapeutic Agricultural Vocational Center
- Project sent out to tender
- Anticipated completion of project: March 2008
XII. Horseback Riding Track
- Final design nearly complete
- Project to be given out to tender in September 2007
XIII. Safari Petting Zoo
- Final design underway
- Project to be given out to tender in January 2008